Construction Progress Report 235

Sep - 12
2018

Construction Progress Report 235

JOB 326-SCAN

Today the well is being installed! Also, the ground is being prepped for asphalt.

 

The stall subfloor has been compacted with clay and ready for the mats.

The stall doors and windows are place, as well as having hardware installed.

The shavings bin is ready for to be sealed, then it will be painted according to the clients color scheme.

 

JOB 326-NEWB

The hardy board is in! It just needs a coat of paint.

 

Stalls are framed out.

 

 

Manure bin has it’s sealant started.

 

The roof is done, just need to paint the cupolas.

 

JOBĀ 326-SPA

This job is complete, with a total project time of just one week.

In all, we removed the lights and plywood, repaired the insulation, and installed hardy board and trim. Then we gave it a fresh coat of paint, and installed new lights.

 

As you can see, the client lost very little time, and is quickly back to work!